February was a busy month on Clay Street. In many ways, KZYX's new home is looking and feeling more like a real radio station headquarters.  We now have furniture in the studios! It might seem like a simple improvement but it is quite complicated to get the right furniture that can bear the load of equipment, not heat up and allow for a good work flow. Furniture specialists Matt and Ray came in on February 19 to do the job.

The building now has a functional employee restroom, and the remaining window coverings have been installed. 

While great progress is being made, we're not just building offices, we are building a state of-the-art broadcast facility, so there is still a ways to go. The studio furniture is a great addition, but we still need to purchase, install and test all the equipment. That will be a costly and time consuming process. In addition to that, there are still quite a few big ticket items that need to be completed before a Certificate of Occupancy will be issued by the city of Ukiah.

These include:

  • Erect the tower

  • Trenching and gas pipe replacement by PG&E to widen site gas line to meet generator specifications

  • Pour concrete pad for the generator

  • Trench in order to connect power to the generator, the parking lot lights, and Building Two

  • Purchase and install antennas and coax cables

  • Build ADA parking space and the sidewalks

  • Install low voltage and ethernet cabling 

  • Exterior painting

  • Landscaping per city and permit specifications